The Big Island and Horse Island areas are closed to public use.
Construction equipment will be utilizing the park road and visitors are asked to take care while walking
and driving the park road, to respect barricades and to follow detours as directed.
February 25, 2025
The bright and sunny days this week has made a dent in the snow pack from the President’s Day weekend storm. The carpenters, plumbers and electricians have all been busy working on interior finishes and on nice days working on the exterior of the buildings. Due to a plan coordination issue the septic system permit for Bathhouse 5 needed to be revised. The permit revision is expected to be submitted to DES on 3/5 and reviewed by the Town of Nottingham on 3/11. Work on Bathhouse 6 was paused for the winter and we plan to pour the foundation next week, weather permitting, and begin construction of the building soon after.

January 27, 2025
It’s been awhile since our last update and winter conditions are a daily challenge for the contractor. The five bathhouses are in various stages of construction and site work is complete at the dump station. Plumbing rough in is mostly complete for buildings 7, 8 and 9. Siding and doors are being installed and interior finishes are starting. It was a race to install the foundations and under slab plumbing once the blasting was complete at buildings 5 and 6 before the cold weather set in.

November 27, 2024
Bathhouses are in various stages of framing and it is nice to see the buildings on the landscape. Septic systems are being installed. To no one’s surprise, ledge has been encountered and will need to be blasted to get the depth needed for septic tanks. Blasting is expected to begin on Monday. A series of horn blasts will sound prior to the blast with a single horn blast sounded when the blast is complete.

.JPG.aspx?width=250&height=187)
.JPG.aspx?width=250&height=187)

November 6, 2024
The 2024 camping season wraps up this weekend at the park. The park road remains open to the public until mid-December or until plowing begins. Under-slab plumbing has been installed and floor slabs have been poured. Lumber for framing and roof trusses have been delivered. The framing crew will began work on bathhouse #5 this week. Ledge removal will continue over the next two weeks.




October 23, 2024
The excavation company has been kept busy removing boulders from building foundation sites and have encountered ledge in places. The contractor will need to blast the ledge to get the elevation low enough to install the foundations and the septic tanks. Foundations for the new bathhouses are being installed and under slab plumbing has begun to be roughed in.




October 9, 2024
The contractors have been busy the last couple of weeks. All bathroom buildings have been demolished and the debris moved off-site. Trees and stumps have been removed at the RV dump station site. In the next two weeks foundations will be poured for the new buildings and excavation for the septic systems will be happening.



